Risk Management Plan
List the risks, assess their severity and probability, and try to consider measures on how the most serious / probable risks could be prevented in advance. In addition, it would be good to have a plan of how to act if the risk materializes. Attach the following section here:
Record the risks to the project in the table below and maintain them as needed. Each risk is given a unique identifier, eg RIS007, as this facilitates their handling in different situations.
| RISK ID | Description | Severity | Mitigation & Notes |
|---|---|---|---|
| RIS001 | Deadline risk | S1 | Regular progress checks (e.g. Scrums), evaluation on what can and cannot be done within given time |
| RIS002 | Labranet Downtime | S2 | Alternative work environment |
| RIS003 | Insecure data handling | S2 | Already existing security issues are to be mapped early in order to estimate allocated time spent on fixes. Possible scope creep |
| RIS004 | Team Member Illness | S3 | Communicate with team, possible re-structuring of weekly tasks if necessary |
| RIS005 | Miscommunication | S4 | Workflow channels only to be used for work |
| RIS006 | Scope Creep | S2 | Define clear objectives and review and compare progress to given scope |
| RIS007 | Low Team Morale | S3 | Keeping up with team members, creating a way to better guide team members on their workflow |
Severity descriptions
The severity class should be defined according the project
| Severity class | Description | Other |
|---|---|---|
| S1 | Total show stopper | |
| S2 | Major issue | |
| S3 | Possible issue | |
| S4 | Inconvenience | |
| S5 | No immediate affect, to be observed |