Status of sprint 00 Date 20.1.2025**
What has been achieved
- Team site and documentation published. We have decited a name for the team and copied the issues of sprint 1. We are finishing getting done with them.
Do we have a problems/challenges?
- N/A
Next steps
- finish sprint 1 and check the check-list
Status of sprint 01 Date 27.1.2025**
What has been achieved
- First daily scrum was held
- Open issues were succesfully imported to issue board
- CSC platform activated and cPouta succesfully launched
- All the PrestaShop source codes forked and pipelines fixed
Next steps
- Sprint planning
- Communication plan
- Risk management plan
- Studying more about PrestaShop
Do we have a problems/challenges?
- Issue with the presta-shop-base-image pipelines, with the help of Narsu it has been solved
Next steps
- Finish sprint 2 and check the check-list
Status of sprint 02 Date 3.2.2025**
What has been achieved
- EPICs selected
- Started working on requirement specification documentation
- Requirement specification documentation finalized
- Project roadmap
- Communication plan
Do we have a problems/challenges?
- No issues detected
Next steps
- Updating the website
- Finalizing documentation to prepare for Gate 01 review
Status of sprint 03 Date 17.2.2025**
- Reviewed Sprint 02 issues
- Docker pipelines passed succesfully
- Working on documentation
Next steps
- Finalizing documentation to prepare for Gate 01 review
- Preparing for Sprint 03
Status of sprint 04 Date 3.3.2025**
- Reviewed Sprint 03 issues
- PrestaShop is now running on docker
- Working on documentation
Next steps
- Preparing for Sprint 05