Status of sprint 00 Date 20.1.2025**

What has been achieved

  • Team site and documentation published. We have decited a name for the team and copied the issues of sprint 1. We are finishing getting done with them.

Do we have a problems/challenges?

  • N/A

Next steps

  • finish sprint 1 and check the check-list

Status of sprint 01 Date 27.1.2025**

What has been achieved

  • First daily scrum was held
  • Open issues were succesfully imported to issue board
  • CSC platform activated and cPouta succesfully launched
  • All the PrestaShop source codes forked and pipelines fixed

Next steps

  • Sprint planning
  • Communication plan
  • Risk management plan
  • Studying more about PrestaShop

Do we have a problems/challenges?

  • Issue with the presta-shop-base-image pipelines, with the help of Narsu it has been solved

Next steps

  • Finish sprint 2 and check the check-list

Status of sprint 02 Date 3.2.2025**

What has been achieved

  • EPICs selected
  • Started working on requirement specification documentation
  • Requirement specification documentation finalized
  • Project roadmap
  • Communication plan

Do we have a problems/challenges?

  • No issues detected

Next steps

  • Updating the website
  • Finalizing documentation to prepare for Gate 01 review

Status of sprint 03 Date 17.2.2025**

  • Reviewed Sprint 02 issues
  • Docker pipelines passed succesfully
  • Working on documentation

Next steps

  • Finalizing documentation to prepare for Gate 01 review
  • Preparing for Sprint 03

Status of sprint 04 Date 3.3.2025**

  • Reviewed Sprint 03 issues
  • PrestaShop is now running on docker
  • Working on documentation

Next steps

  • Preparing for Sprint 05